Friday 21 November 2014

We have a slab


A little update on the last few days. 
Tuesday we saw the rest of the form work completed. 
Wednesday the waffle pods were delivered.
Thursday they installed the waffle pods & steel. 
And then today we went for a visit & as promised we have a slab. 
Tuesday's progress 

Wednesday's the waffle pods delivered

Thursday we saw the waffle pods & steel installed 

And then today our slab poured.

Monday 17 November 2014

Piers today

Rob received a phone call this morning from our site supervisor to let us know they were doing the piers today & said we could go & check the measurements.
We will get a nice credit back as it only came to 48.3lm & we had been quoted for 80lm 😃 the plumbers are there today as well & they have also started to form up. Our site supervisor said the slab will be poured on Friday.

Photo taken in the morning while they were digging the piers.

And this one in the afternoon. Looks like the plumbing is finished too.


Thursday 13 November 2014

Site cut & fill 12/11/14

After what seemed like forever & we'd never get to this stage we have finally started our site works.


 Excited to be starting I went to see if anything was happening after I dropped the kids off at school & found Allworth was hard at work already.

And when I went back in the afternoon it was all leveled & ready to go. Good to see there is no dirt to remove.