Monday 17 November 2014

Piers today

Rob received a phone call this morning from our site supervisor to let us know they were doing the piers today & said we could go & check the measurements.
We will get a nice credit back as it only came to 48.3lm & we had been quoted for 80lm 😃 the plumbers are there today as well & they have also started to form up. Our site supervisor said the slab will be poured on Friday.

Photo taken in the morning while they were digging the piers.

And this one in the afternoon. Looks like the plumbing is finished too.