Update so far. Tuesday I met our ss on site & went through the bottom floor. I wasn't allowed to climb the ladder to see the top floor. I won't be allowed until the stairs are in. Not happy!
Everything is looking great & downstairs looks huge.

The aircon rough in happened on Tuesday & we had to make a quick decision where to put the outdoor unit because where we had decided a tap had been put there but it wasn't on the plan. 

Our ss told me that the porch roof was going on on Tuesday but that didn't happen until Friday. 

The gyprock was supposed to be delivered on Wednesday & the gyprockers to start Thursday or Friday but it was only delivered today. So I'm hoping they will start tomorrow.

Our rain tank got installed on Wednesday  & the insulation was done on Thursday.

I asked if there was a rough estimate of completion & was told not at this time. 

Anyway here is some updated photos

Rain tank installed Wednesday 



Thursday update insulation & the toilet was moved to the side : )


Today's updated photo






3 comments:

  1. Hello Mel&rob, house looking very good and it goes up quick. The colours were very nice. It matches well.Love the brick and they did a good job with the brickwork, it looks perfect! Its nice to see that it all come up together very well. Very good choice, it looks like a proper house that the scaffolding is gone!!!

    ReplyDelete
  2. Hi dcox, thanks we are very happy with the colours. Still deciding if we are going to render or use stacker stone on the porch. Have you started building yet?

    ReplyDelete
  3. Yes we have started! Finally our dream will be a reality soon.Bricks Monday

    ReplyDelete